Our Work · Completed system

East Montgomery County Convention Center: Moderco Panel Repair & Recovery

Project
East Montgomery County Convention Center
Scope
Repair and recovery of 40 riveted Moderco trimless panels
Panel height
30 feet
Status
Completed in 5 days
Thirty-foot Moderco trimless operable partition panels at East Montgomery County Convention Center.

MotionSpan repaired and recovered 40 riveted, trimless Moderco operable partition panels, each standing 30 feet tall, completing the specialized restoration in five days.

Project overview

Specialized repair for 30-foot Moderco panels

Moderco contacted our team directly to repair 40 riveted, trimless operable partition panels at East Montgomery County Convention Center. Standing 30 feet tall, these panels presented a complex repair that demanded experience with their construction and assembly. Moderco trusted our team to restore the existing system.

Two technicians using a scissor lift to repair a 30-foot Moderco operable partition panel.
Thirty-foot panel repairSpecialized repair work performed while the tall Moderco panels remained suspended from the overhead track.

Existing condition

Addressing damage from the original installation

During the original installation, the panels were hung without sufficient additional support at their centers, causing bending and warping in two areas. Their size and riveted construction made the repair especially challenging. Removing the panels from the overhead track would have introduced a risk of further damage, so our team needed to complete the restoration with the panels still suspended in place.

Technicians restoring tall Moderco trimless operable partition panels from a blue scissor lift.
On-track restorationThe existing panels were carefully disassembled and restored without removing them from the track.

Work performed

Careful disassembly and restoration on the track

Our team carefully disassembled the panels while they remained on the track, removing the interior trim to allow the corners to be wrapped before reassembly. This was the most technically demanding part of the project, requiring precise handling and specialized knowledge of these 30-foot-tall trimless panels.

  • Repaired 40 riveted, trimless Moderco operable partition panels
  • Disassembled the panels while they remained suspended from the overhead track
  • Removed the interior trim and wrapped the panel corners before reassembly
  • Skim-coated surface imperfections caused by the installation damage
  • Primed and recovered the panels for a consistent finish
MotionSpan technicians preparing and recovering 30-foot Moderco operable partition panels at a convention center.
Surface preparationSkim coating, priming, and recovery restored a consistent finish across the 40-panel system.

Recovery process

Surface preparation and panel recovery

After reassembly, we skim-coated the surface imperfections caused by the installation damage, then primed and recovered the panels. This coordinated process addressed the damaged finish and restored a consistent appearance across the 40-panel system.

Project outcome

Completed in five days, avoiding costly replacement

By repairing the existing panels, MotionSpan saved the client hundreds of thousands of dollars in removal and replacement costs. The five-day restoration preserved the existing Moderco system and eliminated the need to purchase new panels.

Technicians inspecting and restoring a 30-foot Moderco operable partition panel from a lift.
Specialized field repairCareful field restoration preserved the existing Moderco system and avoided complete panel replacement.

Consultation

Discuss your airwall restoration project.

Request a consultation about operable partition inspection, recovery, repair, alignment, or restoration.

Request a Consultation